Boyd Parallel Interceptor Sewer

Project Overview

This project consisted of 2100 feet of 24″ Sewer Collection Main through a heavily populated and high traffic area of Loveland. Sewer lay depths ranged from 18′-22′. The installation required the relocation of waterline and storm sewer infrastructure, along with coordinating the relocation of many other utilities (electric, gas and telecommunications). Project required extensive public outreach and highly coordinated traffic and pedestrian control. Project challenges included multiple shoring systems, restricted access and groundwater conditions.